Remodeling Permits in Los Angeles

What needs a permit, who issues it, how long it takes, and what happens if you skip it. Written by the team that pulls these permits for our clients.

The Short Answer

Do I Need a Permit?

Usually no permit

  • Painting and wallpaper
  • Replacing flooring with a similar material
  • New cabinets in the same layout
  • New countertops at the same size, with the sink and cooktop staying put
  • Tile and backsplash work

Permit required

  • Moving or adding a sink, toilet, shower or gas line
  • Adding electrical circuits or moving outlets and lighting
  • Removing, moving or opening up a wall
  • Any structural work, including beams and foundations
  • New or enlarged windows and doors
  • Replacing a water heater or re-roofing
  • Room additions, ADUs and garage conversions

Who Issues It

Your Address Decides the Office

If your home is inside the City of Los Angeles, including Woodland Hills, Encino, Tarzana, Sherman Oaks and Venice, permits go through the Los Angeles Department of Building and Safety (LADBS). The city's ZIMAS map shows whether an address is inside city limits.

Cities such as Calabasas, Santa Monica, Burbank, Glendale, Pasadena and Thousand Oaks run their own building departments, each with its own forms and fees. Unincorporated areas, like Marina del Rey, go through Los Angeles County or Ventura County. We confirm the right office for your address before anything is drawn.

Cosmetic work
No permit needed
Simple kitchen or bath
In Los Angeles, often an express permit issued without plan check
Walls or structure
Plans and a plan check review
Additions and ADUs
Usually one to three months in plan check
ADU deadline
State law: a decision within 60 days of a complete application

How It Works

The Permit Process, Step by Step

Plans

Drawings of the work. Anything structural is engineered and stamped by the licensed engineer we work with.

Plan Check

The city reviews the plans and sends corrections. We answer them until the permit is approved.

Inspections

Inspectors check the work in stages, such as framing, plumbing and electrical, before the walls are closed.

Final Sign-Off

A final inspection closes the permit, giving you a clean record for insurance and for the day you sell.

Why It Matters

What Skipping a Permit Can Cost

California sellers must disclose known unpermitted work, and buyers often ask for a lower price or walk away. Lenders may refuse to finance a home with unpermitted additions, and insurers can deny claims tied to work that was never inspected.

If the city finds the work, it can require you to open walls for inspection, permit it after the fact, or remove it. Paying for a permit up front almost always costs less.

What ARKO handles

  • Confirming which office covers your address
  • Plans, with engineering where needed
  • Filing the application under our license
  • Answering every plan-check correction
  • HOA drawings and approvals
  • Scheduling and passing each inspection

See the 17 cities where we've pulled permits ›

Questions

Permit FAQ

Do I need a permit to remodel my kitchen in Los Angeles?
Not for cosmetic work like paint, new flooring, or replacing cabinets and countertops in the same layout. You do need one if you move or add plumbing, add electrical circuits, move walls, or change the layout. In the City of Los Angeles, a kitchen remodel without structural changes can often get an express permit without plan check.
Do I need a permit for a bathroom remodel?
Replacing a vanity, toilet or tile in the same place usually does not need one. Moving a toilet, sink or shower, adding circuits, or opening walls does. Most full bathroom remodels we do involve at least a plumbing or electrical permit.
How long does an ADU permit take in California?
State law requires the city to approve or deny a complete ADU application within 60 days when there is already a home on the lot. Plan check and corrections before the application is complete usually add time, so we plan for one to three months overall.
What happens if I remodel without a permit?
California sellers must disclose known unpermitted work, which can lower your sale price or delay escrow. Lenders may refuse to finance a home with unpermitted additions, and insurers can deny claims tied to unpermitted work. The city can also require you to open walls, permit the work after the fact, or remove it.
Who pulls the permit, me or my contractor?
Your contractor usually does. ARKO pulls permits under our California contractor license #1114425, answers the plan-check corrections and schedules every inspection, so you never have to deal with the city yourself.

General guidance for Los Angeles and Ventura County homeowners, not legal advice. Rules differ by city and change over time, so we confirm the exact requirements for your address during your free consultation.